top of page
Photo Jun 26 2024, 3 01 32 PM.jpg

Box Culvert Extension
Kissimmee, FL

Through 3 separate phases of construction, we extended an existing double barrel culvert and added associated headwalls, along with an additional culvert tied into the same channel. All of these culverts were skewed and attached to existing culverts in order for the contractor to widen the roadway. This scope of work was completed within 5’ of an existing fence line and adjacent neighborhood with no disruption to any existing facility.

bottom of page